Breakdown of Generation Charge

     (A)   (B)   (C)   (D = B + C)   [D / A] 
SOURCE % to Total kWh Purchased  kWh Purchased  Basic Generation Cost (Php)  Other Cost Adjustments (DAA, NSS, & Other Billing Adjustments) (Php)  Total Generation Cost for the Month (Php)  Average Generation Cost (Php/kWh)
NPC-TSC            
BILATERAL CONTRACTS w/ IPPS            
   1. GNPD 105% 8,879,500 84,658,076.61   84,658,076.61 9.5341
IEMOP -5% (407,101) 4,166,682.14 38,688.09 4,205,370.23 (10.3300)
SELF-GENERATION            
SALE FOR RESALE            
OTHERS            
   1. Prompt Payment Discount (Net)       (319,778.33) (319,778.33)  
   2. Pilferage Cost Recovery       (13,144.78) (13,144.78)  
TOTAL 100% 8,472,399 88,824,758.75 (294,235.02) 88,530,523.73 10.4493
Other Generation Rate Adjustment (OGA)            (0.1175)
TOTAL           10.3318

SUPPLEMENTAL BID BULLETIN NO. 07

AMENDMENTS TO THE DRAFT POWER SUPPLY AGREEMENT (PSA) For All Bidders June 8, 2024   Download R8-JCPSP-SBB-No.-07-Additional-Amendments-to-Draft-PSA.pdf Clear Search SUPPLEMENTAL BID BULLETIN NO. 07 FRECOR

Read More »

SUPPLEMENTAL BID BULLETIN NO. 06

ADDITIONAL AMENDMENTS TO THE INSTRUCTION TO BIDDERS (ITB) For All Bidders June 8, 2024   Download R8-JCPSP-SBB-No.-06-Additional-Amendments-to-ITB.pdf Clear Search SUPPLEMENTAL BID BULLETIN NO. 07 FRECOR

Read More »

SUPPLEMENTAL BID BULLETIN NO. 05

AMENDMENTS TO THE DRAFT POWER SUPPLY AGREEMENT (PSA) For All Bidders May 18, 2024   Download R8-JCPSP-SBB-No.-05-Amendments-to-Draft-PSA-Final.pdf Clear Search SUPPLEMENTAL BID BULLETIN NO. 05 FRECOR

Read More »

SUPPLEMENTAL BID BULLETIN NO. 04

AMENDMENTS TO THE INSTRUCTION TO BIDDERS (ITB) For All Bidders May 18, 2024   Download R8-JCPSP-SBB-No.-04-Amendments-to-ITB-Final.pdf Clear Search SUPPLEMENTAL BID BULLETIN NO. 05 FRECOR 8

Read More »

SUPPLEMENTAL BID BULLETIN NO. 03

AMENDMENTS TO THE TERMS OF REFERENCE (TOR) For All Bidders MAY 18, 2024   Download R8-JCPSP-SBB-No.-03-Amendments-to-TOR-Final.pdf Clear Search SUPPLEMENTAL BID BULLETIN NO. 05 FRECOR 8

Read More »

May 2024

Breakdown of Generation Charge Clear Search April 2024 2024 BreakdownBy adminApril 24, 2024Read more March 2024 2024 BreakdownBy adminMarch 25, 2024Read more February 2024 2024

Read More »